Vehicle History

Amphibious Combat Vehicle (ACV): Variants, Specs, Status

By AAAV Published · Updated

The Amphibious Combat Vehicle (ACV) is the US Marine Corps’ eight-wheeled successor to the tracked Assault Amphibious Vehicle. BAE Systems builds it with Iveco Defence Vehicles, and it is derived from the Iveco SuperAV. As of November 2026 the Congressional Research Service lists a planned buy of 608 vehicles in four variants: 389 ACV-P personnel carriers, 33 ACV-C command vehicles, 152 ACV-30 cannon vehicles and 34 ACV-R recovery vehicles, according to its October 2026 In Focus report. That is about half the original objective of 1,122. Initial operational capability came in November 2020 and full-rate production was approved in December 2020. According to CRS, the Navy’s FY2027 budget request “reflects a pre-planned end to Amphibious Combat Vehicle procurement after the program received over $1 billion in FY2026 for final production contracts.”

The vehicle the ACV replaces, and the transition between the two, are covered in the guide to the Assault Amphibious Vehicle. The cancelled tracked program that came between them is told in What Was the AAAV?.

Quick facts

ItemFigure (source)
Prime contractorBAE Systems, with teammate Iveco Defence Vehicles (BAE, June 2018)
Base designEight-wheel drive, derived from the Iveco SuperAV (Shephard, Dec 2016)
Production lineYork, Pennsylvania (Defense News, July 2023); ACV-R work runs through 2029 (BAE, Oct 2026)
Planned total608 vehicles (original objective 1,122)
Crew and load (ACV-P)3 crew and 13 combat-loaded Marines (BAE)
MilestonesLow-rate production June 2018; IOC 13 Nov 2020; full-rate production 8 Dec 2020
Cumulative contract value$2.7 billion face value as of April 2024 (BAE)

Dated milestones, 2015 to 2026

The table puts the competition, the contracts, the safety pause and the variant milestones on one line of dates. It draws on BAE and Marine Corps releases, GAO and DOT&E reports, trade press and the CRS report. Rows marked CRS come from the CRS In Focus report.

DateEventSource
Oct 2015GAO finds most ACV 1.1 activities follow best practices but flags the accelerated schedule and overlapping testing and production as risks; no recommendationsGAO-16-22
Dec 2015A bid protest is filed; it is later denied, but it delays program events and moves developmental testing from February to April 2017GAO-17-402
2017BAE delivers 16 prototypes to the Marine CorpsBAE
Apr 2018GAO puts development cost $59.8 million under baseline and recommends higher manufacturing readiness before later production decisionsGAO-18-364
19 June 2018Milestone C and the production award: options worth $198 million for 30 low-rate vehicles, within options for 204 vehicles worth up to $1.2 billionMarine Corps release; BAE
13 Nov 2020Initial operational capability approved; first vehicles go to 1st Marine DivisionSea Power
8 Dec 2020Full-rate production approved by the Assistant Secretary of the Navy (Research, Development and Acquisition)Sea Power
FY2022First ACV-C vehicles deliveredCRS
19 July 2022Two ACVs have accidents in high surf off California; amphibious operations suspendedCRS
23 Sept 2022Open-water operations resume with a four-foot interim breaker limitCRS
6 Mar 2023Third full-rate production contract, $256.8 million, for ACV-P and ACV-CCRS
1 Feb 2024First production-representative ACV-30 delivered for testingBAE
May 2024First overseas deployment, Exercise Balikatan 24 in the PhilippinesCRS
29 Apr 2025$188.5 million for 30 ACV-30 vehicles, the first lot of full-rate ACV-30 productionBAE
May 2025ACV-30 operational, live-fire and cyber testing completedDOT&E FY2025
14 Jan and 3 Feb 2026$184 million and $195 million contracts for 30 additional ACVs each; BAE says they take ACV-30 orders past 100 and then past 150BAE, Jan; BAE, Feb
28 May 2026BAE announces that operational fielding of the ACV-30 has begunArmy Recognition
30 Sept 2026$230 million modification for 32 ACV-R vehicles; BAE announces it on 8 Oct as $230.1 millionCRS; BAE

A contract is an order, a delivery is a vehicle handed over, and a milestone such as initial operational capability is a decision about capability. The table keeps the three apart. BAE’s releases call the January and February 2026 awards “additional ACVs” but tie both to the cannon variant: the first “brings the total number of ACV-30s ordered to over 100”, and the second raises that total “to more than 150”, against the 152 that CRS lists as planned.

The four variants and their status

VariantRolePlanned quantityStatus as of November 2026
ACV-PPersonnel carrier: 3 crew, 13 Marines389Fielded since IOC in November 2020. More than 200 had been built and 139 had reached units or the schoolhouse by July 2023. BAE said in April 2024 that its fourth full-rate order would complete the fleet requirement for ACV-Ps
ACV-CCommand and control: 3 crew, 7 battle staff33First delivered in FY2022 and in full-rate production in 2023. DOT&E judged it effective as a stationary but not a mobile command post
ACV-3030 mm cannon in a Kongsberg RT-20 remote turret; 3 crew and up to 8 Marines152BAE announced on 28 May 2026 that operational fielding had begun. More than 150 were on order by February 2026, according to BAE
ACV-RRecovery: 2 crew and 2 maintainers, crane and winch34Three production-representative test vehicles delivered by January 2026. 32 production chassis ordered on 30 September 2026; CRS expects the work to end in November 2028, BAE puts it through 2029. The government integrates the Palfinger crane at Anniston Army Depot

Planned quantities come from the CRS report. An April 2026 version of the report gave a 632-vehicle objective, while the May and October 2026 versions list the 608 shown above. CRS describes the 32-vehicle ACV-R award as covering “the full ACV-R acquisition objective”, although its own quantity list shows 34. The $188.5 million ACV-30 award includes fielding support, spare parts and test equipment, according to BAE, and the government buys the turret separately. CRS adds that the vehicle and the turret are integrated at NIWC Atlantic in Charleston, South Carolina.

BAE’s data sheets give the crew details. The ACV-C sheet lists three crew and seven battle staff with satcom, HF/VHF and AFATDS-ready communications. The ACV-R sheet lists two crew and two maintainers, an extendible rotating crane, a heavy-duty winch and a welding and cutting kit.

Planned dates shift between sources. In July 2023 Defense News reported the ACV-30 IOC as expected in the third quarter of FY2026 and the ACV-R IOC in early FY2028. DOT&E’s FY2025 report gave a planned ACV-30 IOC in the second quarter of FY2026, and BAE’s May 2026 fielding announcement, as reported, does not mention an IOC declaration. For the ACV-R, BAE had built and delivered three production-representative test vehicles by January 2026, while work on the 32 production vehicles ordered in September 2026 runs to 2028 or 2029.

Specifications from BAE’s data sheet

BAE’s ACV data sheet, approved for public release in 2018, is the most complete manufacturer source. The comparison column uses BAE’s AAV7A1 RAM/RS data sheet so the two families can be read side by side.

CharacteristicACV (BAE)AAV7A1 RAM/RS (BAE)
Drive8x8 wheeled, H-DriveTracked, water jets
Gross vehicle weight35 tons (32 metric tons)Not stated
PayloadUp to 7,280 lb (3,302 kg)Cargo compartment handles 10,000 lb (4,536 kg) of equipment
Personnel13 plus 3 crew21 troops plus 3 crew
Paved-road speedMore than 65 mph (105 km/h)45 mph land maximum (72 km/h)
Water speed6+ knots, open ocean7 knots (8.2 mph)
RangeUp to 325 miles (523 km) at 55 mph; up to 12 nautical miles at sea followed by 250+ miles ashore200+ miles on land; 7+ hours on water
Length, width, height361 in (9.2 m), 124 in (3.1 m), 114 in (2.9 m) hull height321 in, 129 to 144 in (without and with armor), 130 in
Surf9-foot plunging surf; Sea State 310-foot plunging surf
EngineNew six-cylinder, 700 hp (BAE)525 hp turbocharged diesel
ProtectionBlast-resistant hull, energy-absorbing seats, automatic fire suppressionCan be equipped with armor

Three readings follow from the table. First, the ACV carries fewer troops than the AAV. GAO’s April 2017 report said the AAV can transport 17 Marines (BAE’s sheet lists 21 combat troops) and the ACV 1.1 a minimum of 10 and up to 13, so moving the same number of Marines takes more ACVs than AAVs. Second, the ACV is about 20 mph faster on roads, but its quoted water speed is slightly lower than the AAV’s 7 knots. Third, the ACV’s quoted surf rating is a foot below the AAV’s, and the next section shows why surf matters. Both BAE sheets state that they give only a general description and form no part of any contract, so the numbers are manufacturer figures, not test results.

The open-ocean launch and recovery capability that BAE claims is what ties the vehicle to the Navy’s amphibious ships, described in Well Decks and Amphibious Assault Ships.

The 2022 waterborne-operations pause

On 19 July 2022 two ACVs had accidents during high-surf training off California, according to CRS. One tipped onto its side in the surf zone and another was disabled. Marines in both vehicles returned safely to shore. Amphibious operations were suspended pending an internal review.

Open-water operations resumed on 23 September 2022 under interim limits, including a maximum significant breaker height of four feet. By January 2025 senior Marine leaders said the vehicles were cleared for surf-zone operations after crews completed safety training and certification. Leadership attributed the California incident to operating in 12-foot plunging surf and said, as CRS quotes, “There’s no vehicle that is inherently safe or unsafe.” CRS also records work with BAE on readiness rates and on corrosion of struts and shocks.

Set against the data sheet, three different surf figures are in play. BAE rates the ACV for a 9-foot plunging surf, the accident occurred in 12-foot surf, and the resumption limit was 4 feet of significant breaker height. A manufacturer rating, an incident condition and an operational limit are measured on different bases.

What GAO and DOT&E found

The FY2014 defense authorization act required GAO to review and report on the ACV program annually until 2018. Three of those reports, the last in April 2018, follow ACV 1.1 from development to the production decision.

ReportFinding
GAO-16-22, Oct 2015Most activities followed best practices, but the accelerated schedule and a preliminary design review held after development began posed risks; no recommendations
GAO-17-402, Apr 2017Cost estimate met best practices: about $2.0 billion for development and procurement and $4.2 billion for operations and support (ACV 1.1). GAO recommended delaying the production decision to early FY2019, which DOD did not accept
GAO-18-364, Apr 2018Development estimate $750.7 million against an $810.5 million baseline. GAO recommended manufacturing readiness level 8 before the second low-rate year and level 9 before full-rate production

GAO’s later status notes record both 2018 recommendations as closed and not implemented. The Marine Corps exercised the second low-rate option in December 2018 after a November assessment found readiness level 7, and full-rate production began in December 2020, which the Marine Corps said was at level 8.

DOT&E, the Pentagon’s operational test office, issued its ACV-P report in November 2020 and its ACV-C report in June 2022. Its FY2022 annual report, released in January 2023, found the ACV-C operationally effective as a stationary command post but not as a mobile one. It was suitable and survivable against most threshold ballistic threats, but the embarked staff was limited to a single beyond-line-of-sight net while moving, according to Inside Defense and Defense News. The service later added four beyond-line-of-sight antennas and a network-on-the-move system, Defense News reported in July 2023.

The FY2025 DOT&E report says the ACV-30 finished operational, live-fire and cyber testing in May 2025 and that DOT&E found the testing adequate. It planned a classified combined follow-on operational and live-fire test report for the first quarter of FY2026 and scheduled ACV-R live-fire and operational testing for FY2026 and FY2027. The conclusions of the classified ACV-30 report are not public.

CRS also lists an oversight question for Congress: lessons from Ukraine about vulnerability to anti-tank guided missiles, armed drones and loitering munitions, and whether survivability modifications are under consideration.

How to read ACV announcements

Three habits keep ACV news in order. Match each figure to its variant: the ACV-P carries 13 Marines, the ACV-30 up to eight and the ACV-C seven battle staff. Separate the contract, the delivery and the service decision, since an order such as the $230.1 million ACV-R award buys chassis whose work runs to 2028 or 2029. And read quantities as plans: 608 is a program total, not a delivered count.

Sources